SSC CGL level Solution Set 72 on work time problems 7
Learn to solve 10 Time and Work Problems in SSC CGL Solutions Set 72 in 15 mins. Time and work and Time work wages problems are selected to test you well.
Learn to solve 10 Time and Work Problems in SSC CGL Solutions Set 72 in 15 mins. Time and work and Time work wages problems are selected to test you well.
Solution of maths question set 5 for WBCS teaches how to solve 10 selected arithmetic aptitude questions in 10 minutes. Learn to solve arithmetic in mind.
Solve 10 WBCS arithmetic practice questions of set 5 in 10 minutes. Verify results from answers. Suitable for similar PSC and other aptitude tests.
In 42 days 40 men complete a work. As it happened, instead of all of them working together to finish the job, they started working together, but at the end of every 10th day 5 men left. In how many days would then the work be completed? Rich time and work concept of Mandays technique along with natural number concepts deliver speedy solution...
Learn to solve quickly from Work and Time Questions and Solution Set 10 for SSC CGL Tier 2 using basic and advanced work and time concepts.
Learn to solve 10 Time speed distance questions on train running, boats in rivers and so on in 12 mins using basic to advanced Speed time distance concepts.
Learn to solve speed time distance problems and time and work problems in SSC CGL problems set 44. Basic concepts and techniques used for quick solution.